Sunday, August 12, 2007

I have the bruises to prove it

Though it may not appear from these pics as if I'm doing any work, I promise I am. Quelman and Juan Carlos have a lot of framing experience (they framed the basement, too), and I basically did what they told me. Which, as has been the case for much of this project so far, involved carrying heavy stuff. Pressure treated lumber is no exception...

Notched posts:


Running a line to level the first side of the double-beam:


Setting the joists:








Quelman had a tico nail gun, which I didn't know existed. Made fastening the joist hangers to the ledger board against the house SO MUCH EASIER than hand nailing. We started at 7 on Wednesday morning, and finished at 5 on Thursday afternoon. Not bad for a couple of days work. (I paid them $1000 total for the two days, which is a pretty expensive hourly rate by WV standards. But they worked pretty fast and they did a nice job.)

Ipe comes on Wednesday, all 3,256 lbs of it. I believe I am on the hook for unloading it (story of my summer). Hopefully they can get the truck nice and close to the deck.

Saturday, August 11, 2007

My travelling companion is nine years old




Mookie stayed with me in WV this week after Sarah and the boys left on Tuesday; old as he's getting, he still enjoys a good ride in the car. I think I made him nervous taking these pics (I'm sure I made oncoming drivers nervous).

Here's what the house looked like when I left tonight (I'll get some details up over the weekend). Framing for the deck is finished:


Almost done with the siding:


Won't have enough to do above the windows near the roof, but I need a break from siding anyway:

Thursday, August 09, 2007

Location, Location, Location

Mine is the deck of the ranger station in the Lost River State Park, watching some deer munch on the grass and stealing some wifi. Other people's locations (I know cause they've visited the blog and the blog sees all...): Bulgaria; the Netherlands; Canada; Mexico; Sweden; India; Nigeria; and various and sundry locales in the United States of America. Any of you out-of-towners wondering how hot it was in DC yesterday?

102 degrees.

Got hot here in the mountains of WV, but not that hot, thank goodness. Not so hot that we couldn't get some work done. We started framing the deck yesterday morning, and just finished up about an hour ago. Really looks terrific. Changes the elevation of the house quite a bit. I'll get some pics up over the weekend, along with a recap of the last week or so (Simplex was out to the site for punchlist stuff, Res4 came and saw the house for the first time since the set, and our friends from TV land were here too).

Tuesday, August 07, 2007

Another reason to blog more

I have a long list of things for which I need to thank Res4, and it's time to add publicity to the list. Thanks to an email blast about the progress of our house, I've got lots of new traffic and the onus is on me to keep everybody coming back, heh?

So here's a rough recap: Sarah is eight months pregnant (and was manning the table saw today!); our two boys are managing to entertain themselves at our construction site (gravel, gravel, and more gravel) while we try to finish the siding and frame the deck; my brother Craig and his friend Carter are off to parts unknown so I've lost my captive labor; still no water or electric; the basement is framed and we've got an electrician starting our rough wiring tomorrow. My ambition was to finish this house all on our own - earn some sweat equity, pat ourselves on the back for a job well done. And while we've definitely saved some money (and our cedar siding looks awesome), we're not setting any land speed records. The reality is that grad school starts back up for me again at the end of the month and my "summer vacation" is almost over. So I'm gonna put in as much time as I can at the site but also start farming some more things out that we were initially hoping to do ourselves. We'll still be saving some money by acting as our own GC, but we'd really love to get some renters in by leaf season and that ain't gonna happen if I'm still out here on the weekends in the fall working on the plumbing...

Long story short - we're hoping to finish by early September, we're keeping a list of names of people we've heard from about making reservations (send any inquiries to lostrivermodern AT gmail DOT com), and we'll keep getting pics of our progress and updates about money posted as often as we can.

Friday, August 03, 2007

What's YOUR basement look like?

Here's how ours shapes up at the moment. Framing lumber:


Insulation:


Our tiny little bit of remaining cedar:


Which we hope will cover what's left to be sided (basically all the white) on the front of the house. Gonna be VERY close:

Deck Status

Here are our deck post bases, which aren't all precisely the same distance from the house, but were set at the same height and will do just fine:


All our pressure treated lumber for the deck is on the site; I need to get the ledger on the house and then we're ready to go. Ipe is ordered (1300 linear feet of 5/4" x 6" x 8' boards at $3.34/ft from Mike at Austin Wholesale Lumber; came to just under $5000 with the $700 delivery charge). Haven't bought any of the materials for the posts/railing system yet - Feeney stainless steel cable system is what Res4 spec'd.

Thanks Mrs. Gates

Our lovely neighbor across the street granted an easement to the power company to bring a line across her yard to the bottom of our driveway (the main power line runs behind her house). The power company began work earlier this week - clearing a path and setting a pole in her backyard:


The power company tells us, however, that our proposed transformer location (which I understood they had approved) is too far from the house - 360 feet, a distance that makes carrying the right amp service difficult. I assume fixing this problem is going to mean digging up our conduit and that is going to mean more money, but I haven't caught up with my excavator yet...

Monday, July 30, 2007

Still no pics

But I've been taking lots of them. And I'll be back home (sleeping in a real bed, instead of on an eggcrate) on Thursday. So lots of pics by the weekend.

Craig and Carter leave at the end of the week. They've gotten just about all the siding finished and the cabin looks great. I'm waiting for my Cembonit color samples to arrive in the mail so I can get my order in. And I'm just about to bite the bullet and order my ipe. I'll get some money updates posted when I get home too.

Thursday, July 26, 2007

And ANOTHER thing...

Just kidding. (Actually, I need to find a roofer cause my contractor ordered all the wrong materials and that'll be the last mistake he makes for me. But more on that later.)

Back from vacation and a quick trip to WV - the cabin really looks terrific with the siding on (three sides just about finished). I've got lots of pics but I left my camera's USB cable in the Adirondacks, so they'll have to wait for awhile. In the meantime, here's what's new at the site since I was last there: Craig is apparently a magnet for hummingbirds, and Carter does a fantastic Christopher Walken (Carter does the True Romance scene, but I've decided to keep this blog family friendly). The deck footers are poured. The Guest House has apparently found out about us, so we might meet some of our neighbors soon (hopefully they won't catch on to our secret plan to steal all their customers). Simplex will have a crew out to the site next week to do some punchlist stuff. John and Joe from Res4 will be out to visit on Wednesday (on their way home from speaking here - if you're anywhere near Richmond, definitely check it out). I think our friends from TV land will be at the site then too. Turns out the Lost River State Park has had wifi all this time and I didn't know it - so now I can update the blog from WV (as if I don't spend enough time posting here as it is). And I'm back out there tomorrow morning.

Monday, July 23, 2007

One more complaint

I'm back out to West Virginia tomorrow morning to supervise the buildout of the roof eave. But first one more note about things that haven't gone quite right. My rough budget numbers for the siding and deck were premised on the rough numbers in my contractor bids. And because I never walked though the details of the bids with the contractors (cause I knew we were going to do lots of it ourselves), the numbers for the siding and the deck were, it turns out, rough. Nobody (least of all me) priced the cost of the materials spec'd in the drawings into their bids for those items. But it turns out top-grade cedar and ipe are - surprise, surprise - very expensive. So the cost of the siding and the deck materials alone are approaching the contractor bids for those parts of the job. Good thing we're doing it ourselves...

So that's really a complaint about myself. I could/should have priced those materials beforehand. It wouldn't have changed anything, I don't think; though we've kept costs down on our finishes on the inside of the house, the mat'ls for the exterior are really important to us. I just wish (as the balance in our operating account dwindles) I'd been more meticulous about planning out each and every cost. One thing about DIY is that you're gonna spend more money than you think, so the more costs you know about beforehand, the more predictable the money will be.

Saturday, July 21, 2007

Post- (really Media-) Mortem

So I'm on vacation. (Some of my friends and family would say I've been on vacation since work began on this cabin, and others would say I've been on vacation since I quit being a lawyer.) Ironically, my vacation finds me trading a construction site in West Virginia for a construction site in Tupper Lake, NY (home of the Wild Center), where my in-laws have a cabin that was supposed to be renovated in the spring and ready for our arrival, but we all know how that goes.

Without any new pics to show off, this seems like the right time to catalog some of the messiness of our little prefab project. First, some context. As a rule, I'm a pretty low stress person. I take most stuff in stride. And this cabin's premise - occasional second home and (hopefully) more regular rental - means that mistakes aren't the end of the world. So the breeziness of my take on some of the ups and downs of this process probably isn't representative of how many people deal with the nuts and bolts of building a new home. (Some poles on the how-stressed-do-you-get scale: AustinMod and ModHampton, both of which I should have linked to by now). There are been lots of instances in which a different person - with different things at stake - would have been justified in being really exorcised. So here are a few of those.

First, when the house arrived, it was apparent that very few of the final punchlist items had been resolved by Simplex. None of them were major, but the most significant item - a slider column that was out of plumb in the factory - meant that the house was open to water infiltration where the slider door should have met the jamb but didn't. I knew that Simplex would send a crew to resolve these issues, and I know punchlist stuff can take a while to resolve, but it was disappointing nonetheless that items we had identified hadn't been dealt with (and we actually still haven't even resolved these unfinished punchlist items - we'll have a conversation about them this week).

Then the day our set was scheduled to occur was a ridiculous mess. Joe and John from Res4 had come all the way from NYC, and as soon as we all got to the site it was obvious that we were not going to go forward. The hitch for the bulldozer was woefully inadequate for the weight of the house. The weight of the house was info that the contractor had been given months before, and it wasn't until the bulldozer operator showed up that morning that the contractor told him how much the house weighed, at which point the operator balked. What's more, the crane operator showed up that morning and said he wouldn't do the job with the size crane they had already spec'd for us, another absurd last-minute change of heart. (I can't imagine anything that I could have done to anticipate either of these items, so I don't have any good advice about how to prevent this other than to have more competent contractors than the one I've chosen for myself.) So we rescheduled, and after lots of rain delays we pulled the house up the hill a week later, and set it a couple of days after that.

I haven't said a lot here about the trip of the house from the bottom of the driveway up to the homesite. We'd known since the beginning of this whole project that difficult sites are not ideal for prefab and that we might suffer for our hubris in choosing land with access issues. I also knew early on that my contractor was prone to giving answers I wanted to hear as opposed to being frank about potential problems. (NB - this is a difficult tendency to discern in the first couple of meetings you might have with potential GCs/contractors/builders, but one that can present huge trouble. I'd suggest that you really push people you interview on where they envision problems occurring. You'll probably already know some of the tricky spots. Are they frank? Do they sugarcoat it?) I knew that our road was going to be hard to get our house up. I didn't know in what ways. At the end of the day, the biggest problem was that the grade of the road meant that the trailer couldn't turn the corner without the back end of the trailer dragging. Which meant that as the bulldozer continued up the turn, and the front end of the trailer continued to go up with it, the back end of the trailer sat in one spot and rotated, like the point of a compass. As the front of the trailer got higher, the wheels of the trailer - located underneath the midline of the house - supported less and less of the weight of the house, until finally they were off the ground, and the bulldozer was basically trying to drag the whole weight of the house, which was resting on only the back end, which was stuck in the ground. When this happened, the front end of the house was probably about eight feet higher than the back end, and the trailer was bowing pretty low in the middle, which meant that the house itself was bowing quite a bit, and it was really visible in the window and slider frames (which were trapezoidal during the worst of the stress). Now we'd all talked through this quite a bit beforehand. We talked about getting a hydrolic dolly to slide the trailer laterally, and about winching the trailer laterally. But I have to say that once the trip up the hill started, no one really seemed to be in charge. There were two different bulldozer operators, my contractor, and many different laborers, and everyone was so focused on trying to move the house that I was the last person anyone was paying any attention to. So while I watched the house bend (and wondered if it might actually just collapse), I really wanted to scream STOP and make everybody back up and start over, doing all the things we'd talked about doing. But that's a hard thing to know when to do, and an even harder thing to actually do. We ended up putting sections of telephone pole between the wheels and the end of the trailer and got the trailer moving again that way. The house settled down, but much of the distortion in the window and slider frames remained. We had no idea how much damage was done or what would be required to remediate it.

Our first task in the days after the house was set was to take all the trim off the windows and sliders and see what was what. Res4 was pretty sure that we were going to be ok - their experience has been that houses settle down quite a bit once they're set. And they were more or less right - turns out everything could just be reshimmed/leveled/plumbed - not the end of the world. But the sliders need to be worked on from the outside, and we can't do that until the deck or some scaffolding is over on that side, and that hasn't happened yet. All in all, the stress on the house seems not to have had any lasting effect - I didn't want to blog it until we knew the extent of the issue. But it was a huge question mark after the fact, and one that preoccupied me for a little bit.

The one lesson I keep coming back to in my mind from these episodes is the importance of the people you have working for you. Simplex, in spite of some minor nits, has been great in terms of communication so far, and I fully expect that whatever little issues we have will be resolved. Res4 I cannot say enough good things about. My contractor - well, I could have done a better job vetting and managing him, I suppose. A couple more odds and ends and he'll be finished, and I'll have nobody to blame for any of my troubles but myself.

UPDATE: I guess another lesson here is that this house is tough. While it did look to me like the house could have crumbled in light of the stress it was under, it didn't, and no one else was ever worried about that. Res4 didn't really flinch when I told them about it, and told me some stories about similar situations with other sets where the houses came through fine even if the owners' nerves were a bit frayed. I'd never seen a house move like that, and I didn't know they could. But this one did, and it appears to be no worse the wear.

Thursday, July 19, 2007

Concrete Feet

No, not these. These:


It's the footer/column for our deck posts - a Sonotube, a cardboard tube for pouring concrete columns, set atop a Square Foot, which forms the footer for the column. So instead of pouring footers and waiting for them to cure and then pouring the columns, you pour the whole thing in one shot. (Craig found the Square Feet through Dan Cook, a real cool guy at United Rentals in Frederick, MD.)

The guys at the site set these forms today (I am on vacation! - more on that later); concrete should come anytime. Then we can get going on the deck. Sounds like the electrical meter/panel connections are finished, as is site grading and the pump for the well.

Tuesday, July 17, 2007

Trim

Craig and Carter finished the trim on the uphill side of the house:



Sunday, July 15, 2007

Rough carpentry

I got tired of climbing in and out of the house all the time, so I made these little steps, which Craig promptly fell down once it got dark (2x6 treads are not ideal for 6'5 guys, and I'm sure don't meet code):


The excavators are scheduled to finish burying the conduit tomorrow, and then they'll move up to the site to begin grading. That'll make getting in and out of the house easier, and we'll be able to set up scaffolding to begin fastening the upper reaches of the siding.

We were supposed to have our electrical "inspection" on Saturday (scare quotes because all they check is the exterior meter connections and the connection at the panel). But we had to push it off cause our contractor didn't set the meter socket on Friday like he promised. Not too big a deal, but I can't get the power company to begin the process of getting power to our site until that's done (and with the conduit just about in we're almost ready for power to be connected).

The well folks should be out this week to finish their connections (they brought the water line into the basement last week; now they need to install the pressure tank). Lumber for the deck and framing the basement will come this week after grading is finished and we have someplace to put it. We should pour footers for the deck posts this week. Concrete polishers come next Monday to do the basement floor.

I'm out at the site for the next couple of days.