Sunday, June 03, 2007

Rough Schedule

So this is what we look like right now:

Week of June 4: Dig footers, excavate utility trench, order cedar siding; factory finishes box;

Week of June 11: Pour foundation, walk-through inspection of box at factory, my brother Craig arrives for the summer to help the finishing of the basement;

Week of June 18: Box arrives and is set. Anybody want to come?

We'll see how close we can stick to this. I've got a lot to blog about the prep process that's going on right now for the rest of the work we have to do, and some of the difficult parts of this process and managing it ourselves. But more on that later.